Why your solar farm connection agreement is taking longer than quoted
Connection agreements slip because a project down the road gets connected first, which forces your site to be remodelled to account for it. Michael…
0:18What's really causing renewable connection delays in Queensland now
The current bottleneck is access to network operators, not the engineering. Michael Day explains how constrained operator resources create a queue…
0:13How network operators assess solar connection applications now
Both sides of the connection process have matured, and proponents now arrive better prepared than they did a few years ago. Michael Day, GM…
0:16What happens after you lodge a grid connection application
Once your application is lodged it joins the network operator's queue. Michael Day explains why staying at the top of that queue comes down to how…
0:15Rooftop solar vs solar farm: where network approval actually changes
Approval time scales sharply with system size. Michael Day walks through where the process genuinely changes: cookie cutter under 30kW, growing…
0:38Why your feed-in tariff doesn't match the spot price
Daytime solar floods the network, so the grid does not need more bulk generation and spot prices frequently go negative. Michael Day explains why…
0:31Contract for difference vs spot price, explained for project sponsors
Most energy in the NEM is not traded at the spot price. Michael Day explains contracts for difference and PPAs in plain terms, and why the spot price…
0:28If not the spot price, where is electricity actually bought and sold?
Contracts for difference and PPAs carry the bulk of NEM volume. Michael Day explains how AEMO settles at spot between two parties while separate…
0:17Why solar developers use offtake agreements instead of the spot market
Solar farms are capital intensive investments over ten to twenty years, and bankers will not fund that against a volatile spot price. Michael Day…
0:40Has Queensland's battery build-out killed the arbitrage opportunity?
Queensland's battery build-out has flattened the daily price curve and shrunk the arbitrage spread that existed a few years ago. Michael Day explains…
0:46How batteries actually get paid to discharge into the grid
Batteries earn from the spot price in five minute intervals, from PPAs and contracts for difference, from cap markets, and from FCAS. Michael Day…
0:34Who sets battery connection standards under 5MW in Queensland
For systems under 5MW in Queensland, Energy Queensland sets the rules through STN 1175 for high voltage and STN 1174 for low voltage, covering all…
0:38How a battery connection application differs from a solar farm's
A battery both draws from and discharges to the grid, so network operators assess minimum and maximum night-time loadings as well as daytime flows…
0:24Where renewable energy certificates come from and why they're worth it
Large-scale and small-scale certificates are created by renewable systems and surrendered each year by retailers acting as liable entities. Michael…
0:17Why renewable energy certificate prices move outside your control
Certificate prices move because they are an openly traded product responding to supply and demand, not to anything happening at your site. Michael…
0:20How a nearby data centre affects your solar project's approval time
A large new load connecting nearby changes the network dynamics in your local area, which can force your project to be remodelled with that load…
0:17Why data centres keep coming up when you're connecting a solar farm
Data centres are adding significant load to a network that has not seen real load growth in years. Michael Day explains why that can work in a…
0:24Why a utility asks an outside firm to help write its own standards
QGE has assisted Power and Water in the Northern Territory with their connection standards. Michael Day explains why a smaller utility brings in…
0:28How much politics really affects renewable project approvals
Politics is close to everything in renewables. Michael Day explains how fifteen years of shifting climate policy has affected both investment…