Why your solar farm connection agreement is taking longer than quoted

Connection agreements slip because a project down the road gets connected first, which forces your site to be remodelled to account for it. Michael Day, GM Renewables and Energy at QGE, explains why that rework cycle turns grid connection into a race to be first, and what it means for your project timeline.

Full transcript
So one of the biggest delays that we see on a a project getting its connection process is rework because a project down the road has just got their connection and then that triggers the remodeling of your site to include all of the subsequent projects. So that that's what drives us into a race to get first connection with the network.

Topic: Network Connections

Presenter: Michael Day