For systems under 5MW in Queensland, Energy Queensland sets the rules through STN 1175 for high voltage and STN 1174 for low voltage, covering all embedded generation. Michael Day explains where the Clean Energy Council standards apply instead, and why 1 to 5MW is still a grey area.
Full transcript
So battery connection standards for systems under 5 megawatts in Queensland, they're driven by Energy Queensland. So Enerjax and Urggon, they have a standard STN 1175 for the high voltage connected systems and 1174 for the low voltage. That actually covers all renewable generation or uh diesel reciprocating engines etc. So any of the the embedded generation comes under those two standards. Battery specific standards though are typically driven predominantly by the CEC on the smaller scale. So anything up to 200 kilwatt hours is very heavily governed by the CEC. Larger systems in the 1 to 5 megawatts are a little bit more of a gray area.