Network Connections
Rooftop solar vs solar farm: where network approval actually changes
Approval time scales sharply with system size. Michael Day walks through where the process genuinely changes: cookie cutter under 30kW, growing network interest above that, a clear transition past 1.5MW, and substantial review beyond 30MW.
Full transcript
The approval times for a small residential scale solar system is quite short and it extends rapidly as the system size increases. On a a 30 kowatt and below, it's very much a cookie cutter approach where the network doesn't take too much investigation into it, provided we we stick to the standards. Beyond that, the network starts taking an increasing interest in the system design and modeling its impact on the network. Above 1 and a half megawatt, we see another transition. And so that's on your larger commercial industrial systems. And then beyond 30 megawatt again, the network starts to take a much more substantial review of the system and how it impacts the network. That then causes those delays in connection processes.